Software Project Management

Project Schedule

Press Plan.

Early and late dates, in weeks from the start of the project
Task Weeks Early start Early finish Late start Late finish Float

How it works

The critical path method goes through the tasks twice. Forward: a task starts when all the tasks before it are finished, and with a start-to-start link — when the other task has started. Backward: the late dates are the latest ones that do not move the end of the project. The float of a task is the difference between its late and early start. The tasks without float form the critical chain: a delay of any of them delays the whole project. The darker bars of the chart are the critical tasks, the dashed frames show the float.

From the course

  • Semester 6
  • Course work: a project schedule with finish-to-start and start-to-start links
  • The project on this page is made up

Useful resources

  1. Critical path method the article from the Wikipedia