Project Schedule
Press Plan.
| Task | Weeks | Early start | Early finish | Late start | Late finish | Float |
|---|
How it works
The critical path method goes through the tasks twice. Forward: a task starts when all the tasks before it are finished, and with a start-to-start link — when the other task has started. Backward: the late dates are the latest ones that do not move the end of the project. The float of a task is the difference between its late and early start. The tasks without float form the critical chain: a delay of any of them delays the whole project. The darker bars of the chart are the critical tasks, the dashed frames show the float.